Haradutta Biradutta Bhawan

Present status

  • All dismantle works has completed.
  • Carrier Make Central A/C including duct Completed: 8.5 × 4 A/C for Audience part 5.5 ×1 A/C for Stage Part 44 Ton A/C
  • Entire Celling of the Auditorium has been Covered by Acoustic Board 50×24. glass wool on every board covered by a Heary white plastic sheet.
  • Side wall of the Auditorium from Ground level up to 8/ will covered by high quality wooden Acoustic panel. This Materials is reach at Bangalore Airport and on 20.7.2021, it is loaded on Bangalore Ghy. Super Fast train. We expect to reach it at Ghy. Rly. Goods Godown by 26th of July/2021.
  • Side wall from the height 8/ to celling is already covered by perforated Acoustic 2/×2/ Gypsum Board observing the Guideline of Acoustic Auditorium.
  • Totally damaged Floor-of Audience sitting part has been renovated up to 4// to 5// C.C... works.
  • Green Room also renovated including Roof Trust/Roof Tins/Floor tiles/Running Water/Toilet lock/ Electrification/ etc.
  • Right side Veranda already upgraded.
  • Panel Board has already built.
  • Installing all electrical equipment's.